EDGE to put another two quality landmarks on the Dubai skyline.

August 4, 2019
20190802_183424-2.jpg

A new construction milestone was reached at The Hilton Garden Inn Hotel and Embassy Suites project. The Raft of a 30 storey tower in Business Bay was cast on Thursday and Friday last week in a 20-hour continuous pour of 3,200 cubic metres of concrete. EDGE works closely with all sub-consultants MAK Structural Engineers, SEED MEP Engineers, contractor Gulf Asia and client appointed Project Management Consultant and QS Faithful and Gould to ensure that project progresses on time and within the budget. The adjacent Holiday Inn Hotel and Kingston Residences, another 30 storey tower, as seen piled and excavated in the background will be cast in the next few weeks.